05-08-2016
Works in Katowice in progress
1. Work related to the execution ground and humus
2. Completed installation of the ventilation system
3. Work related to the loading of biofiltr
4. Completed installation and mechanical commissioning were carried out on transport lines
5. Completed installation and commissioning were carried out mechanical devices technological line conveyors in stock RDF
6. Completed installation of fire detection system in the RDF hall
7. Work is underway on a system of leachate retention
8. Completed installation of pumping system:
• rainwater
• technological
• percolate
9. Completed installation of aeration system for the ripening process biostabilization and composting and winter compost storage
10. Safety training begins next week.