Commissioning of Waste Treatment Plant
Commissioning of Waste Treatment Plant (ZUO) in GDAŃSK - SZADÓŁKI
The contract between our company and Vauche SA established the following tasks:
- preparation of necessary documents to carry out installation's start-up
- management, reporting and control of installation during final and operational tests
- compost testing in terms of required mass losses of bio-fraction in the process of aerobic stabilization
- consulting activities during tests performed for Vauche company
- safety training for Investor’s staff
- elaboration of health and safety instructions
- elaboration of the operating instruction for ZUO Gdańsk Szadółki (in Polish and English)
Location
Szadółki
Execution date
03.2011 - 12.2011
Scope of works
commissioning of sorting and composting installations
in ZUO Gdańsk-Szadółki
Plant's capacity
210 000 Mg/year